Project required breaking down equipment, changing filters, replacing a ruptured disk, as well as assisting with blinding and resolving ancillary mechanical issues that arose from the outage.

Industry
Fertilizer

Process
Urea Ammonium Nitrate
(UAN Plant)


Project Type
Emergency Outage

Project Duration
7 Days

Scope
Emergency Urea Ammonium Nitrate Plant Repairs & Mechanical Support

Business Unit
Specialty & On-Site Services